  CURRENT STATUS

Start of Construction

  1. Roads and Infrastructure – January, 2005
  2. Main Works – June, 2005

Commissioning

  • Unit-I - 20th Jan, 2008
  • Unit-II -28th Jan, 2008

Commercial Operation Date (COD) – 6th Feb, 2008

Project has already completed more than four (4) years of its commercial operation. Yearly generation data is detailed below. Since its commissioning in January 2008, the Project has been generating and supplying much needed uninterrupted power to HPSEB network. M/s. Energy Infratech Pvt. Ltd. is engaged to provide the expert services for O&M of this Project. Proper O & M procedures and MIS reporting system have been evolved & are being rigorously implemented.

Monthly Generation Data since commissioning